Course 01 · Lesson 10 of 13

The 90-day plan

Founders only2 min read

Owners by role; dates internal. Must blocks money, launch or law.

When Action Owner Priority
Weeks 1 to 3 (19 Oct to 8 Nov) Launch inventory and acceptable-bug line; payment test, refund, tranche logic; T&Cs, privacy notice, founding terms; website gate fixes Dom, John, Alex, Karl Must
Weeks 1 to 3 Design partner terms (D4): shortlist 15 in week 1, three recruited and one live by 6 November; personal messages to all warm contacts; D22 owner named, fallback walkthrough by 2 November; SPICED logging and weekly dashboard Alex, John Must
Weeks 1 to 3 D1 reading with Dom and Neil explaining the data flows (Must before any engagement line changes); D20 lawful basis, no sends until then; D12 owner and fix date, D10 and D13 confirmed in writing Karl, Dom, Neil Should
Week 4 (9 to 13 Nov) Launch week; every inbound lead answered within two working days; first beachhead review, direction only Alex, John Must
Weeks 5 to 10 (16 Nov to 27 Dec) Weekly design partner calls; read the first activation cohorts; decide D28 before the founding close message; one plain early-December message: the date and the bands, once, no countdown Product owner, John, Founders Must
Weeks 5 to 10 Alex declares the date his posts are drafted through Holly; affiliate pack (D19, approved copy, "Ad" rules, claims check); one law firm with a written mutual action plan by 27 November Alex, Karl Should
Weeks 11 to 13 (28 Dec to 17 Jan) Founding rates close on 31 December or when a band fills, with no extension, rename or reopening. From 1 January, Standard live under D28, every Standard conversation logged as pricing data Founders, John Must
Weeks 11 to 13 Onboarding model and customer success cover (D31) and the salesperson trigger (D25) decided; expo follow-up booked; next version of this strategy Founders Should

What slips first. Karl (part-time), ranked: 1. T&Cs, privacy notice and founding terms (they block money); 2. D1; 3. D20; 4. the legal answers pack, D27; 5. D21 terms if D28 needs them; 6. affiliate "Ad" rules and D9 advice. Slips first: 6, then 5, then 4. Items 1 and 2 never slip. Dom (the only developer), ranked: 1. launch bugs, payment and tranche logic; 2. launch inventory; 3. website gate fixes; 4. billing counter or fallback; 5. the D1 data-flow walkthrough; 6. D12, D10 and D13 in writing; 7. activation reporting; 8. the free tool; 9. website polish. Slips first: 9, then 8, then 7 (John counts activation by hand). Bug fixes never slip. Dom has no weekly reporting duties.